Hollow-pile construction

Hollow-Pile

CONSTRUCTION PROCESS

The process starts out in the same way as a solid pile with a temporary casing sunk through the upper layers of unstable ground into the clay below. The casing is then drilled out to the required depth. Once this is complete a steel tube is dropped down into the hole to create the void at the centre of the pile and a 1m-deep plug of concrete is placed at the foot to provide the pile’s end-bearing capacity. Concrete is then carefully poured in the void between the steel tube and surrounding earth using a specially fabricated tremmie; this approach was used to ensure the concrete completely filled the narrow void. Once this is complete a specially designed pile cap is cast in order to distribute the load into the hollow section.Currently the inner tube remains in place once the concrete has set, however, future developments may allow for this tube to be removed with the concrete having further reinforcement.

PERFORMANCE

Testing was carried out on a 1200mm diameter solid pile and a 1200mm diameter hollow pile that had an 800mm diameter central void. The test results came out in the hollow pile’s favour. Under the design load of 4500kN the settlement of the solid pile was 3.9mm compared to 4.3mm for the hollow pile, well within the tolerances. As the loads increased the hollow pile outperformed the solid version. At 1.5 times the working load the solid pile sunk 11.9mm compared to 8.5mm for the hollow version, and when tested to failure the ultimate load carried by the hollow pile was 9,000kN, about 1,150kN higher than the solid pile.

www.bbge.com

 

 

You are here: Area of expertise Hollow-pile construction